Virgin to Start Laying Rails in January

Virgin Rails USA had told an Orlando news outlet that is will begin laying rails in January 2020 for its extension from West Palm Beach to Orlando, Florida.

The carrier said it will begin construction in February 2020 of a $70 million, 138,000 square foot maintenance center that it said will create 160 new jobs.

The 170-mile line to Orland will have 55 bridges that will cost $35 million apiece. Virgin projects that each bridge will take 12 to 30 months to build.

“Obviously our goal is to maximize mobility for the Central and South Florida communities,” said Virgin Trains USA CEO Patrick Goddard said. “We are looking at stations. We are in a dialogue with the Treasure Coast, we are in a dialogue with the Space Coast. We would like to see stations every 50 to 60 miles. I think that’s feasible and reasonable to have an express train service so we will continue to pursue to update those as we make progress.”

Virgin said the steel being used in construction of the line is being purchased from American Steel in Fort Wayne, Indiana. Approximately 1,000 will be employed to build the line.

Goddard said before building west of Orlando International Airport that Virgin must reach an agreement on a lease from the Central Florida Expressway Authority and the Florida Department of Transportation.

Virgin plans to build along existing highways between Orlando and Tampa.

Tags: , , ,

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.


%d bloggers like this: