New Middletown Depot Construction Delayed

A new Amtrak station for Middletown, Pennsylvania, is not expected to open until sometime in 2021 or 2022.

The Pennsylvania Department of Transportation said it will take a couple years before construction can begin to build a new platform and station.

PennDOT attributed the delay to track work yet to be performed by Norfolk Southern.

NS must relocate about a mile of its track at a cost of about $6.5 million to make room for relocating two tracks that will be used by Amtrak.

“Given the uncertainty of the railroads’ track schedules, a firm completion date was never set,” said PennDOT spokesman Richard Kirkpatrick said. “Track work construction schedules are contingent upon the availability of the Amtrak and Norfolk Southern workforces.”

The new station is expected to cost $24.4 million and replace the existing depot on Mill Street. That facility is not accessible to handicapped individuals. The new facility will be built along Route 230 at the end of Ann Street.

Kirkpatrick said the station design is being reviewed by Amtrak.

A public-private partnership known as Keystone Connections has submitted a preliminary proposal to build the station and related developments.

Keystone has not yet released many details on the project other than it expects to construct a 400-space parking area and that there will be room for retail shops and possibly a hotel.

The station project also includes a pedestrian bridge to be built over Route 230 that will link the Penn State Harrisburg campus to the station and downtown Middletown.

Planning for the station project began in 2009. Middletown is served by Amtrak’s Keystone Service trains between New York and Harrisburg, Pennsylvania.

Tags: , , , , , ,

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.


%d bloggers like this: